In October 2018, we shared a Community Update for our plan which detailed:
• The role of the MA&CNP steering group and the need of a Guys Marsh representative
• Where to find the questionnaire results
• Plans for a Community Feedback Day (Spring 2019)
• A timeline of the neighbourhood process (see below)
• A Call for Sites

A summary of the anticipated timeline is indicated below:

MA and CNP 31 Timeline (anticipated)

Nov 17 M A and C designated as a neighbourhood area by NDDC

Jan -Feb 18 Community Questionnaire

Mar 18 Analysis of community questionnaire

June 18 Formation of local steering group

Ongoing 18 Gathering evidence base

Winter 18 Draft objectives and polices

Early 19 Community Feedback Day

Spring 2019 Draft Neighbourhood Plan

Summer 2019 Community consultation on Draft plan (Reg 14)

Autumn 2019 Revised plan based on consulation responses

Winter 2019 Plan submitted to Local Planning Authority (Submission Version)

Early 2020 Consultation on Submission Version (Reg 16)

Early 2020 Examination

Mid 2020 Referendum
 
A summary of the October Community Update was also included in the December edition of the Spreadeagle.


Update May 2018/March 2019


The results of the questionnaire  were analysed in May 2018 and can be found here http://www.melburyandcann.co.uk/files//MA&CNP31%20Questionnaire Analysis May.Final.pdf

N.B. this includes an updated version with additional analysis, including a breakdown of responses answering 1-5 is available.


The results were analysed by Development in Transition (DinT).    https://www.developmentintransition.co/